FLOOR PLAN HIGHLIGHTS
This beautifully designed home offers the perfect balance of comfort, functionality, and sustainable living.
PHOTO COLLAGEOFF-GRID CAPABILITIES & SUSTAINABLE FEATURES
Our eco-friendly home is designed for complete off-grid living with sustainability at its core. Solar Power System
VideoINTERACTIVE CAD MODEL-linkTOUCH AND DRAG AREA TO VIEW BI-DIRECTIONAL - will open on a new page
|
Cast in Place - 10 Person Crew Size- Can Reuse Forms Hundreds of Times
Foundation Slab ( 4 Days )- set up formwork, plumbing, rebar pour concrete, strip forms, Wall Concrete Cast in Place( 10 Days) -set up formwork, plumbing, Electrical.rebar pour concrete, strip forms, Roof Concrete Cast in Place (15 Days)-set up formwork, plumbing, Electrical.rebar pour concrete, strip forms Cabinet Concrete Cast in Place ( 3 Days ) -set up formwork, plumbing, pour concrete, strip forms Exterior and Interior Coatings (4 Days ) - Prep work, Spray, Clean Up Metal Doors and Fiberglass Windows (2 Days )- Insall Appliance and Mechanical Install ( 4 Days)- Install Site Clean Up ( 2 Days ) Other Work ( 6 Days ) Grace Period Days ( 10 Days ) Total Working Days For Turn Key Completion ( 60 Days ) 3d Printed - 5 Person Crew Size | Uses about 30% Less Concrete
Foundation Slab ( 3 Days )- Set up Printer, plumbing, rebar print concrete slab, Pattern Floor, Can use printer to mark plumbing trenches Wall Concrete 3d Printed ( 2 Days)- Walls, Plumbing, and Electrical Roof Concrete 3d Printed (5 Days)- 3d Printed in 2 Days, Ready to crane in 3 Days, Break Down Printer ( 1 Day )- Note: Printer has been on project site for 7 Days- Now can be ready to move to next project Cabinet Concrete Cast in Place ( 3 Days ) -set up formwork, plumbing, pour concrete, strip forms Exterior and Interior Coatings (4 Days ) - Prep work, Spray, Clean Up Metal Doors and Fiberglass Windows (2 Days )- Insall Appliance and Mechanical Install ( 4 Days)- Install Site Clean Up ( 2 Days ) Other Work ( 6 Days ) Grace Period Days ( 10 Days ) Total Working Days For Turn Key Completion ( 50 Days ) BENEFITS OF OFF-GRID, SUSTAINABLE LIVING
|